PROJECT OVERVIEW:
The Campus Drive Traffic Calming Project spans 0.78 miles of Campus Drive between 2nd Street and Hayward Boulevard. The area is served by multiple neighborhoods, California State University East Bay, hiking trails, churches, senior facility, and Fire Station 9. Hayward identified Campus Drive as a priority corridor for traffic calming improvements based on community concerns, traffic volume, speed and collision data, and other factors. The purpose of the project is to identify pedestrian, bicycle, and traffic calming improvements to address traffic safety concerns and mobility needs in the corridor that are supported by the community.
Sidewalk Improvement
The project will provide a sidewalk route from 2nd Street to University Court on Campus Drive and builds on improvements initiated in February 2023, which included striping upgrades with bike lanes and bollards along Campus Drive from 2nd Street to Highland Boulevard.
Sidewalk improvement will cover approximately 2,700 linear feet split between either side of the roadway and includes the following improvements along Campus Drive:
- Installing a 4.5-foot sidewalk on the East side of Campus Drive from near 2nd Street to Oakes Drive
- Installing Curb ramps at the intersection of Campus Drive with Oakes Drive
- Installing a 4.5-foot sidewalk on the West side of Campus Drive from Oakes Drive to University Court
- New Stormwater Treatment Area on east side of Campus Dr at University Court.
These improvements build on the goals of the Campus Drive Traffic Calming Project, which aimed to reduce vehicle speeds and enhance safety for all users, including pedestrians, bicyclists, motorists, and transit riders. By providing a sidewalk connection, protected bike lanes, and consistent roadway features, these measures will create a safer, more accessible, and more efficient environment for everyone.
Upcoming Meetings:
There are no meetings scheduled at this time.
PROJECT DOCUMENTS:
June 27, 2023 - Community Announcement Letter
Apr. 19, 2023 - Community Meeting
The Hayward Transportation Division held an online public meeting at 6:00 p.m., Wednesday, April 19, to discuss the outcome of the Pilot Program and to get your feedback on next steps.
Jan. 26, 2023 - Campus Drive Traffic Calming Project – Pilot Program Initiation Letter
A letter was sent to residents on and near Campus Drive to alert them to the start of the Pilot Program in mid-February.
Jan. 20, 2022 Community Meeting
Aug. 11, 2022 Community Meeting
The Hayward Transportation Division held a second online public meeting on Thursday, August 11 to discuss proposed traffic calming improvements on Campus Drive.