The new La Vista Park will take shape north of the extension of Tennyson Road east of Mission Boulevard and is planned as an active and passive recreation destination for the entire city—with 180-degree-plus San Francisco Bay views from a ridge trail, sports fields and courts, an amphitheater, yoga lawn and much more

The park project will remake and reclaim for public use the old La Vista Quarry.  It was originally planned as part of a 179-home subdivision next to the quarry by the quarry owner, DeSilva Gates, of Dublin.  As part the 2005 city approval of the development, DeSilva Gates is required to contribute up to $2.14 million to the now estimated $23.5 million cost of La Vista Park—but only incrementally as each new home is sold.

The recreation district is committing voter-approved Measure F1 bond proceeds and the city is pledging park “in lieu” fees on several future real estate development projects.

La Vista Park is located north of Tennyson Road and east of Mission Boulevard. The park will feature:

  • 180-degree-plus San Francisco Bay views
  • hiking trails
  • sports fields and courts
  • an amphitheater
  • yoga lawn
  • and more

The City of Hayward will oversee the building of the park with the Hayward Area Recreation and Park District (HARD).

Check out the park’s approved designed:

Concept Photos

Project Timeline

  • Start Construction Documents – Competed 30% documents; updating CEQA
  • Complete Construction Documents – Summer of 2021 (earliest) or Summer of 2022 or 2023 (if CEQA permitting needed)
  • Start Construction – 3 months after completing construction documents
  • Complete Construction – 12 months after start

Project Documents

Jul. 22, 2020 Council Infrastructure Committee Meeting

Mar. 26, 2019 City Council Meeting

Award of Professional Services Agreement to SurfaceDesign, Inc., (SDI); Award of Professional Services Agreement to Langan; Appropriation of Funds; and Amendment of Resolution 18-081

Nov. 13, 2019 City Council Meeting

Informational Report regarding The DeSilva Group Conducting Partial Grading at the Future La Vista Park Site

May 15, 2018 City Council Meeting

Project Status & Funding Direction

Jan. 30, 2018 City Council Meeting

Joint Work Session with Hayward City Council and Hayward Area Recreation and Park District Board of Directors: La Vista Park Final Presentation from Surface Design Inc. and Funding Discussion

Oct. 30, 2017 City Council Meeting

Joint Meeting to Receive Updates on La Vista Park and Other Projects