TIME LINE FOR ADMINISTRATIVE USE PERMITS, SITE PLAN REVIEW AND VARIANCES (ADMINISTRATIVE ACTION)

TASK

MAXIMUM TIME FOR COMPLETION

CUMULATIVE TIME

 Submittal of Application 

 

 

 File Set Up, Account Number Established 

 2 working days 

 2 days 

 Project referred to other City departments, responsible and trustee agencies, neighborhood task forces, residents and tenants within 300’ of property, and other known interested parties.*

 14 calendar days 

 16 days 

 Responses coordinated and interdepartmental meeting held regarding project. 

 5 working days 

  21-23 days

 Applicant advised of status of application (completeness) and may be asked to provide any other information required to review plans. 

 1 day 

  22-24 days

 If necessary, Applicant prepares revised plans and submits additional information necessary to continue processing permit. 

 In accordance with applicant’s schedule. 

 

 If revised plans are submitted, they may be re-circulated for review. Conditions of approval are prepared. 

 5 working days 

  27-29 days

 If the project is exempt from environmental review, the Planning Director approves or denies the project and provides public notice. There is a 15-day appeal period.** 

 15 calendar days

  42-44 days

 *If initial referral to the public indicates there is opposition to the project, or if the scope of the project merits review before the Planning Commission, the application will be treated as a conditional use permit, and that process will be followed. 

 ** If during the public notice period the project is appealed, the application will be scheduled before the Planning Commission and the time line for a conditional use permit will be followed. 

 

DOWNLOAD PDF

 

 

TIME LINE FOR CONDITIONAL USE PERMITS, SITE PLAN REVIEW AND vARIANCES (PLANNING COMMISSION REVIEW)

TASK

MAXIMUM TIME FOR COMPLETION

CUMULATIVE TIME 

 Submittal of Application  
 File Set Up, Account Number Established 
2 working days
2 days
 Project referred to other City departments, responsible and trustee agencies, neighborhood task forces, residents and tenants within 300’ of property, and other known interested  parties.
14 calendar days16 days
 Responses coordinated and interdepartmental meeting held regarding project.5 working days21 - 23 days
 Applicant advised of status of application (completeness) and may be asked to provide any other information required to review plans.
1 day
22 - 24 days
 Applicant prepares revised plans and submits additional information necessary to continue processing permit.
In accordance with applicant's schedule 
 Applicant submits revised plans, which may be re circulated for review. Determination is made whether project is categorically exempt from CEQA or if a negative declaration is  required. *
5 working days27 - 29 days
 Planning Commission report, conditions and findings are prepared and circulated for in-house review. *
10 working days39 days
 Public Notice provided and project scheduled for next available Planning Commission hearing.
12- 30 calendar days, depending upon hearing dates
51 to 69 days
 Ten-day appeal period. ** 61 - 79 days
 * If a negative declaration is required, additional time will be necessary to prepare and post the environmental document.
 
 **If appealed, the application to sent to City Council for final action, which adds approximately four weeks to the process.

 