TIME LINE FOR ADMINISTRATIVE USE PERMITS, SITE PLAN REVIEW AND VARIANCES (ADMINISTRATIVE ACTION) | ||
|---|---|---|
TASK | MAXIMUM TIME FOR COMPLETION | CUMULATIVE TIME |
Submittal of Application |
|
|
File Set Up, Account Number Established | 2 working days | 2 days |
Project referred to other City departments, responsible and trustee agencies, neighborhood task forces, residents and tenants within 300’ of property, and other known interested parties.* | 14 calendar days | 16 days |
Responses coordinated and interdepartmental meeting held regarding project. | 5 working days | 21-23 days |
Applicant advised of status of application (completeness) and may be asked to provide any other information required to review plans. | 1 day | 22-24 days |
If necessary, Applicant prepares revised plans and submits additional information necessary to continue processing permit. | In accordance with applicant’s schedule. |
|
If revised plans are submitted, they may be re-circulated for review. Conditions of approval are prepared. | 5 working days | 27-29 days |
If the project is exempt from environmental review, the Planning Director approves or denies the project and provides public notice. There is a 15-day appeal period.** | 15 calendar days | 42-44 days |
*If initial referral to the public indicates there is opposition to the project, or if the scope of the project merits review before the Planning Commission, the application will be treated as a conditional use permit, and that process will be followed. | ||
** If during the public notice period the project is appealed, the application will be scheduled before the Planning Commission and the time line for a conditional use permit will be followed. | ||
TIME LINE FOR CONDITIONAL USE PERMITS, SITE PLAN REVIEW AND vARIANCES (PLANNING COMMISSION REVIEW) | ||
|---|---|---|
TASK | MAXIMUM TIME FOR COMPLETION | CUMULATIVE TIME |
| Submittal of Application | ||
| File Set Up, Account Number Established | 2 working days | 2 days |
Project referred to other City departments, responsible and trustee agencies, neighborhood task forces, residents and tenants within 300’ of property, and other known interested parties. | 14 calendar days | 16 days |
| Responses coordinated and interdepartmental meeting held regarding project. | 5 working days | 21 - 23 days |
Applicant advised of status of application (completeness) and may be asked to provide any other information required to review plans. | 1 day | 22 - 24 days |
Applicant prepares revised plans and submits additional information necessary to continue processing permit. | In accordance with applicant's schedule | |
Applicant submits revised plans, which may be re circulated for review. Determination is made whether project is categorically exempt from CEQA or if a negative declaration is required. * | 5 working days | 27 - 29 days |
Planning Commission report, conditions and findings are prepared and circulated for in-house review. * | 10 working days | 39 days |
Public Notice provided and project scheduled for next available Planning Commission hearing. | 12- 30 calendar days, depending upon hearing dates | 51 to 69 days |
| Ten-day appeal period. ** | 61 - 79 days | |
* If a negative declaration is required, additional time will be necessary to prepare and post the environmental document. | ||
| **If appealed, the application to sent to City Council for final action, which adds approximately four weeks to the process. | ||