Fiscal Year 2026 Pavement Improvement Project

Image
Photo of a truck and a machine roller paving a street in Hayward.
Gading Road pavement rehabilitation, Summer 2025

The City of Hayward annual Pavement Improvement Project (“PIP”) will begin late-May 2026 and will bring more than $10 million in street and curb repairs, resurfacing, striping, and bike lane, crosswalk, and other upgrades to more than 129 lane-miles of roadway.

The project encompasses 123 street segments and is expected to be completed by the end of November. Residents will receive 72-hour notice of the exact time of work in their neighborhoods from project contractor Bay Cities Paving & Grading, Inc.  

Street segments included in the Fiscal Year 2026 Pavement Improvement Project have been selected based on City evaluation of current pavement conditions, input from the public and City Council, grouping of streets by neighborhood for cost and schedule efficiency, and available funding.

The City’s annual Pavement Improvement Project is funded through Alameda County Measure BB sales tax revenue, gas tax revenue, state vehicle registration fees, street system improvement funds, and the California Road Repair and Accountability Act of 2017.

Questions? Contact

Project Manager, Yama Farouqi: (510) 583-4761 or yama.farouqi@hayward-ca.gov

List of Streets

Explore previous, current, and projected street paving locations using the interactive map below.

To navigate to the 2026 map:

  1. Click Map Layers in the upper right corner of page.
  2. Click the arrow “>” to expand treatment years.
  3. Click “2026 Project Paving Work.”

Paving History and Projected Paving Map

STREETLIMITSTREATMENT
Albatross Rd.Breaker Cir. to Breaker Cir.Preventative Maintenance
Albion Ct.Breaker Cir. to Cul-De-SacPreventative Maintenance
Beachwood Ct.Cul De Sac to Marshbrook Dr. (End) Preventative Maintenance
Beachwood St. Marshbrook Dr. to Spindrift Cir.Preventative Maintenance
Breaker Cir.Marshbrook Dr. to Marshbrook Dr. Preventative Maintenance
Breaker Ln.Marshbrook Dr. to Marshbrook Dr. Preventative Maintenance
Driftwood St.Marshbrook Dr. to Spindrift Cir.Preventative Maintenance
Dune Cir.Sandcreek Dr. to Sandcreek Dr.Preventative Maintenance
Eden Park Pl.Hesperian Blvd. to Cul-De-SacPreventative Maintenance
Eden Shores Blvd.Marina Dr. to Hesperian Blvd.
Marina Dr. to Begin PCC
Begin PCC to End PCC
End PCC to Eden Shores Dr
Preventative Maintenance
Eden Shores Ct.Eden Shores Dr. to Cul-De-SacPreventative Maintenance
Eden Shores Dr.Eden Shores Blvd. to Eden Shores Ct.Preventative Maintenance
Isle Ct.Shellgate Cir. to Cul-De-Sac Preventative Maintenance
Jetty WayEden Shores Dr. to Eden Shores Dr.Preventative Maintenance
Marina Dr.Industrial Blvd. to Eden Park Pl.Preventative Maintenance
Marshbrook Dr.Eden Shores Dr. to Eden Shores Dr.Preventative Maintenance
Plover Ct.Marshbrook Dr. to Cul-De-SacPreventative Maintenance
Sandcreek Dr.

Edenshores Blvd. to Tern Pl.

Shellgate Cir. to Edenshores Blvd.

Preventative Maintenance
Sea Drift Cir.Eden Shores Dr. to Eden Shores Dr.Preventative Maintenance
Sea Drift Ln.Eden Shores Dr. to Sandcreek Dr.Preventative Maintenance
Sea Haven Ct.Eden Shores Dr. to Cul-De-SacPreventative Maintenance
Sea Horse Ct.Eden Shores Dr. to Cul-De-SacPreventative Maintenance
Shellgate Cir.Shellgate Ct. to Sandcreek Dr.Preventative Maintenance
Shellgate Ct.Shellgate Cir. to Cul-De-SacPreventative Maintenance
Spindrift Cir.Marshbrook Dr. to Marshbrook Dr.Preventative Maintenance
Spindrift Ct.Marshbrook Dr. to Cul-De-Sac Preventative Maintenance
Sunset Dune WaySandcreek Dr. to Shellgate Cir.Preventative Maintenance
Tern Pl.Eden Shores Dr. to Sandcreek Dr.Preventative Maintenance
Santa Clara St.A St. to Winton Ave.Preventative Maintenance
Foothill Blvd.Mission Blvd. to Apple Ave.Preventative Maintenance
Harder Rd.Santa Clara St. To Mission Blvd. Preventative Maintenance
Hesperian Blvd.City Limits to City LimitsPreventative Maintenance
Huntwood Ave.Whipple Rd. to San Antonio St. & Folsom 
Ave. to Gading Rd.
Preventative Maintenance
Jackson St.Santa Clara St. to Mission Blvd.Preventative Maintenance
Mission Blvd.A St. to South City LimitsPreventative Maintenance
Santa Clara St.Harder Rd. To Winton Ave.Preventative Maintenance
Tennyson Rd.Hesperian Blvd. To Mission Blvd.Preventative Maintenance
Whipple Rd.City Limits To City LimitsPreventative Maintenance
A St.Walnut Ave. to I-880 NB Off-Ramp Rehabilitation
Hathaway Ave.West A St. to City LimitsRehabilitation
Martin Luther King Dr.Staley Ave. to Burbank St.Rehabilitation
A St. Foothill Blvd. to County LimitsRehabilitation
Fifth St.C St. to B St.Rehabilitation
Grace St.Peralta St. to Montgomery St.Rehabilitation
Grove Way & Locust St.Grove Way and Locust St.Rehabilitation
Kimball Ave.Rio Vista St. to Foothill Blvd.Rehabilitation
Main St.A St. to Warrant St.Rehabilitation
Oakview Ave.Rio Vista St. to Foothill Blvd.Rehabilitation
Rio Vista St.

End to End

Hazel Ave. to Rex Rd.

Rehabilitation
Seventh St.B St. to EndRehabilitation
Sixth St.B St. to C St.Rehabilitation
Sylvan Glen Ct.Second St. to EndRehabilitation
Western Blvd.Peralta St to City Limits Rehabilitation
Western Blvd.Smalley Ave. to Sunset Blvd.Rehabilitation
Austin Ave.Cypress Ave. to Huntwood Ave.Rehabilitation
Berry Ave.Silverthorne Pl. to ACFC (COP)Rehabilitation
Edith St.Sycamore Ave. to Lilly Ave.Rehabilitation
Groom St.Lilly Ave. to Cul-De-SacRehabilitation
Lilly Ave.Groom St. to Edith St.Rehabilitation
Orchard Ave.Soto Rd. to Joyce St.Rehabilitation
Pinedale Ct.Mission Blvd. to EndRehabilitation
Sycamore Ave.Mission Blvd. to Edith St.Rehabilitation
Traynor Ct.Cul De Sac to Traynor St.Rehabilitation
Waterson Ct.Traynor St. to Cul De SacRehabilitation
Ainslee Ct.Cul De Sac to Whitman St.Rehabilitation
Colette St.Sorenson Rd. to South EndRehabilitation
Diana Pl.Luvena St. to EndRehabilitation
Ebony WayJoshua St. to Voltaire St.Rehabilitation
Fruitwood WayVoltaire St to Whitman St. Rehabilitation
Jane Ave.Whitman St. to Harder Rd. Rehabilitation
Laurette Pl.Colette St. to Cul De SacRehabilitation
Mahogony St.Edwin Way to Cottage Park Dr.Rehabilitation
Sorenson Rd.Collette St. to Luvena Dr.Rehabilitation
Stanislaus WayStanislaus Ct. to West End Cul De SacRehabilitation
Voltaire St.Stanislaus Way to Edwin Way Rehabilitation
Adeline St.Eldridge Ave To Blaine WayRehabilitation
Belvedere Ct. Shepard Av to CDS Rehabilitation
Brian St.Bruno St. to Baldwin St.Rehabilitation
Conant Ct.Rieger Ave To EndRehabilitation
Eldridge Ave.Inglewood St. to Regal Ave.Rehabilitation
Huntwood Ct.Huntwood Ave to End Rehabilitation
Lyford St.Lytelle St. To Rieger Ave.Rehabilitation
Orchard Park Pl.Schafer Rd. to Cul-De-SacRehabilitation
Ranker Pl.Manon Ave. to CDSRehabilitation
Rieger Av.Hamrick Ave. To End Rehabilitation
Stanwood Rd.Inglewood St. To Underwood Rd.Rehabilitation
Tampa Ave. Tennyson Rd. to Patrick Ave.Rehabilitation
Underwood Ave.Inglewood St. to Gomer St. Rehabilitation
Cinnamon Ct.Ruus Rd. to Cul De SacRehabilitation
Colony Ct.Folsom Ave. to Vagabond LnRehabilitation
Folsom St.Ruus Rd. to Tampa Ave.Rehabilitation
Foxfire LnLogan Way to EndRehabilitation
Sebring Ct.Welford Ln to Cul-De-SacRehabilitation
Silverdell WayHuntwood Ave. to Colony Ct.Rehabilitation
Thiel Rd.Ruus Rd. to EndRehabilitation
Vagabond LnFolsom Ave. to Colony CtRehabilitation
Breakwater Ct.Breakwater Ave. to Clawiter Rd Rehabilitation
Clawiter Rd.Enterprise Ave. to UPRRRehabilitation
Enterprise Ave.Clawiter Rd. to Whitesell St.Rehabilitation
Point Eden WayEden Landing Rd. to Cul-De-SacRehabilitation
Research Rd.Point Eden Way to Trust Way Rehabilitation
Trust WayResarch Rd. to Eden Landing Rd. Rehabilitation
Viking St.Diablo Ave. to Depot Rd.Rehabilitation
Anna St.Denton Ave. to Buchanan Way Rehabilitation
Ardenwood Ct.West St. to Dead EndRehabilitation
Bennington Ln.Dodge Ave. to Cryer St.Rehabilitation
Brentwood Ct.Sangamore St. to End Rehabilitation
Calaveras Rd.Denton Ave. to Buchanan WayRehabilitation
Chapman Ct.Cryer St. to Cul De SacRehabilitation
Christina Ct.Monument Blvd. to Cul De SacRehabilitation
Heather Ct.West St. to Dead EndRehabilitation
La Playa Pl.La Playa Dr. to End Rehabilitation
Stone Ct.Sangamore St. to EndRehabilitation
Verlor Ct.Sangamore St. to End Rehabilitation
Xavier Ave.Monument St. to Chandler Rd.Rehabilitation
Yew Ct.Sangamore St. to West St.Rehabilitation

Project Documents

April 21, 2026 — City Council

Adopt a Resolution Awarding a Contract to Bay Cities Paving & Grading, Inc., for the FY 26 Pavement Improvement Project, Project No. 05347, in the Amount of $10,063,947.60 and Authorizing an Administrative Change Order Budget of $1,436,052.40

Feb. 24, 2026 — City Council

Adopt a Resolution Approving Plans, Specifications, and Call for Bids for the Fiscal Year 2026 Pavement Improvement Project No. 05347

June 3, 2025 — City Council

Adopt a Resolution Authorizing the City Manager to Execute a Professional Services Agreement with Pavement Engineering, Inc., to Provide Engineering Services for the Fiscal Year 2026 Pavement Improvement Project No. 05347 in a Not-to-Exceed Amount of $339,020