Fiscal Year 2025 Pavement Improvement Project (PIP)

Construction Workers paving streets

The City of Hayward is gearing up to start its annual pavement improvement project bringing over $12.5 million of spot repairs, micro surfacing, pavement grinding and overlay, curb ramp upgrades, and restriping, including bike lane and crosswalk improvements to more than 41 lane miles of roadway.

The project is expected to start in June 2025 and completed by end of November 2025.

65 streets segments are to be included in the Fiscal Year 2025 Pavement Improvement Project. Residents will receive a 72-hour notice of the exact time of work provided by the contractor, DeSilva Gates Construction.

Street segments included in the Fiscal Year 2025 project have been selected based on City evaluation of current pavement conditions, public and City Council input, grouping streets by neighborhood for cost and schedule efficiency, and available funding.

The City’s annual Pavement Improvement Project is funded through a combination of Alameda County Measure BB, gas tax revenue, state vehicle registration fees, street system improvement funds, and the California Road Repair and Accountability Act of 2017.

Questions? Contact

Project Manager, Yama Farouqi: (510) 583-4761 or yama.farouqi@hayward-ca.gov

List of Streets

VIEW THE FULL MAP HERE DOWNLOAD THE PDF LIST & MAP

Map Key:

STREET

LIMITS

TREATMENT

Broadway Street (1)East 10th Street to East 12th StreetPreventative Maintenance
Broadway Street (2)East 16th Street to Mission Blvd. Preventative Maintenance
Calhoun StreetMission Blvd. to EndPreventative Maintenance
Douglas StreetMission Blvd. to EndPreventative Maintenance
East 10th StreetCul-De-Sac to Jefferson StreetPreventative Maintenance
East 11th StreetCul-De-Sac to Jefferson StreetPreventative Maintenance
East 13th StreetTennyson Road to Hancock StreetPreventative Maintenance
East 15th StreetWebster Street to Calhoun StreetPreventative Maintenance
Hancock Street (1)East 10th Street to Mission Blvd. Preventative Maintenance
Hancock Street (2)Mission Blvd. to East 16th StreetPreventative Maintenance
Hayward Blvd. (1)Carlos Bee Blvd. to change of pavement colorPreventative Maintenance
Jefferson StreetMission Blvd. to East 10th StreetPreventative Maintenance
Kellogg AvenueMission Blvd. to Calhoun StreetPreventative Maintenance
Monticello StreetEast 12th Street to Mission Blvd.Preventative Maintenance
Amador StreetElmhurst Street to Winton AvenueRehabilitation
Bishop AvenueEvergreen Street to Harder RoadRehabilitation
Broadway Street (3)East 16th Street to EndRehabilitation
Clawiter Road (1)Breakwater Avenue to SPRR Tracks Rehabilitation
Clawiter Road (2)Breakwater Avenue to Eden Landing RoadRehabilitation
Crocker AvenueWiegman Road to Huntwood AvenueRehabilitation
Cypress AvenueHarder Road to Jackson StreetRehabilitation
D Street (1)Watkins Street to Grand StreetRehabilitation
D Street (2)Grand Street to Winton AvenueRehabilitation
Delta CourtWiegman Road to EndRehabilitation
East 12th StreetTennyson Road to Jefferson StreetRehabilitation
East 16th Street (1)Webster Street to Calhoun StreetRehabilitation
East 16th Street (2)Cul-De-Sac to Webster StreetRehabilitation
Encina StreetRieger Avenue to EndRehabilitation
Evergreen StreetHarder Road to Regal AvenueRehabilitation
Jackson StreetSilva Avenue to EndRehabilitation
Jennings WayHamrick lane to Eldridge AvenueRehabilitation
Gading RoadPatrick Avenue to Harder RoadRehabilitation
Genstar RoadSan Luis Obispo Avenue to Salmon WayRehabilitation
Gomer AvenueUnderwood Avenue to Tampa AvenueRehabilitation
Hayman StreetWhipple Road to San Antonio StreetRehabilitation
Hayward Blvd. (2)Change of pavement color to Parkside DriveRehabilitation
Hayward Blvd. (3)Parkside Drive to Civic AvenueRehabilitation
Hayward Blvd. (4)Civic Avenue to Farmhill DriveRehabilitation
Industrial ParkwayHuntwood Avenue to Mission Blvd. Rehabilitation
Medallion DriveWhipple road to San luis Obispo AvenueRehabilitation
Oharran DriveTennyson Road to Cole PlaceRehabilitation
Orchard AvenueMuir Street IntersectionRehabilitation
Pacific StreetTennyson Road to Spanish Ranch IIRehabilitation
Salmon WayGenstar Road to Huntwood AvenueRehabilitation
San Antonio Street (1)San Luis Obispo  Avenue to Zephyr AvenueRehabilitation
San Antonio Street (2)Zephyr Avenue to Huntwood AvenueRehabilitation
San Benito Street (1)San Luis Obispo Avenue to Zephyr AvenueRehabilitation
San Benito Street (2)Zephyr Avenue to endRehabilitation
San Clemente StreetSan Luis Obispo Avenue to Zephyr AvenueRehabilitation
San Luis Obispo AvenueHuntwood Avenue to San Antonio StreetRehabilitation
Santucci CourtSandoval Way to Cul-De-SacRehabilitation
Santana StreetZephyr Avenue to Crocker AvenueRehabilitation
Sutro StreetMeek Avenue to Chase AvenueRehabilitation
University Court (1)Quail Canyon Court to Highland Blvd.Rehabilitation
University Court (2)Highland Blvd. to EndRehabilitation
Webster Street (1)Mission Blvd. to East 16th StreetRehabilitation
Webster Street (2)East 10th Street to East 12th StreetRehabilitation
Whipple Road76 Gas Station Driveway to 24 Hour Fitness DrivewayRehabilitation
Wiegman Road (1)Zephyr Avenue to Crocker AvenueRehabilitation
Wiegman Road (2)Whipple Road to Zephyr AvenueRehabilitation
Winton Avenue (1)Soto Road to D StreetRehabilitation
Winton Avenue (2)Eastern Abutment to Soto RoadRehabilitation
Winton Avenue (3)Amador Street to Western AbutmentRehabilitation
Zephyr Avenue (1)Wiegman Road to Huntwood AvenueRehabilitation
Zephyr Avenue (2)Huntwood Avenue to Hayman StreetRehabilitation

Project Documents

 

Apr. 22, 2025 — City Council

Adopt a Resolution Awarding a Contract to DeSilva Gates Construction LLC, for the Fiscal Year 2024-2025 Pavement Improvement Project, Project No. 05338, in the Amount of $12,570,061 and Authorizing an Administrative Change Order Budget of $949,939

Apr. 22, 2025 — City Council

Adopt a Resolution Approving the Project List for Fiscal Year 2025-2026 Road Repair and Accountability Act (RRAA) Funding for the Fiscal Year 2025-2026 Pavement Improvement Project

Feb. 25, 2025 — City Council 

Adopt a Resolution Approving Plans and Specifications and Call for Bids for the FY 25 Pavement Improvement Project, Project No. 05338

Apr. 23, 2024 — City Council

Adopt a Resolution Awarding a Contract to MCK Services, Inc., for the FY24 Pavement Improvement Project, Project No. 05242, in the Amount of $12,365,204.50 and Authorizing an Administrative Change Order Budget of $969,795.50

Mar. 5, 2024 — City Council

Adopt a Resolution Approving Plans and Specifications and Call for Bids for the FY24 Pavement Improvement Project

May 16, 2023 — City Council

Adopt a Resolution Approving the Project List for FY2024 Road Repair and Accountability Act (RRAA) Funding for the FY2024 Pavement Improvement Project

Apr. 25, 2023 — City Council

Adopt a Resolution Authorizing the City Manager to Execute Amendment No. 5 Increasing the Professional Services Agreement with Pavement Engineering, Inc., by $517,540, for a Total Not-to-Exceed $2,273,035 to Provide Engineering Services for the FY24 Pavement Improvement Project 05242